The vacuum cast casing lead time for one part is about 18 working days, counted from wax tooling release to shipment. Wax tooling takes 5, shell build and bake 6, pour and clean 2, heat treatment 2, and machining with two scans 3. The number is a working-day estimate for one part and it moves with section thickness and inspection scope.
The shell is the longest single stage, not the pour. Five ceramic layers dried at 22 °C and 50 % relative humidity take 8 hours each, so the shell alone consumes about two working days before the bake. The bake at 900 °C for 2 hours is short by comparison, but it cannot start until the last layer is dry.
Wax tooling is the second fixed block. Cutting a tool for a 2.5 mm wall and proving the first wax pattern takes 5 working days at this wall thickness, and it is on the critical path because nothing else can start until the tool exists.
Pour, clean and cut add 2 working days, most of it in-mold cooling and shell removal rather than melting. The melt itself is minutes; the casting sits in the shell for 60 minutes before it is allowed to move.
Tooling time is set by wall thickness and feature count, not by part size. A 2.5 mm wall needs a tool that fills without a cold shut at the far end of the cone, so the first shots are cut and checked before the tool is signed off. That iteration is where the 5 days go.
The tool also fixes the datum for everything after it. A wax pattern outside ±0.10 mm pushes the correction into machining, which adds a day rather than saving one.
One part and a hundred parts share the same tooling block. The difference appears in the shell and pour stages, where a batch can share a bake but cannot share a dry.
Heat treatment contributes 2 working days and cannot be compressed by much. Cleaning, radiography to ASTM E192 level 2 and cutting leave stress in the casting, so it enters the furnace within 24 hours of cut-off: 1180 °C solution treatment for 1 hour with 2 bar argon cooling, then 850 °C stress relief for 2 hours with furnace cooling.
A superalloy heat treatment cycle of that shape is a two-day block once loading, cooling and the 24-hour re-measurement are counted. Cutting it shorter does not remove the wait; it moves the risk into machining.
The cast-to-machine handoff is what makes the chain predictable, and it is the part of the vacuum cast casing lead time where a day is easiest to lose. A part that is measured before it is stable is measured twice, and the second measurement is the one that costs a day.
Stage | Value | Unit |
|---|---|---|
Wax tooling | 5 | working days |
Shell build and bake | 6 | working days |
Pour and clean | 2 | working days |
Heat treatment | 2 | working days |
Machining and two scans | 3 | working days |
Total, one part | 18 | working days |
Shell layer drying | 8 | hours per layer |
A rush schedule can compress tooling and machining by running them in parallel with the shell, and it can add a second shift at the machine to shorten the vacuum cast casing lead time at the end of the chain. It cannot dry a ceramic layer faster than the binder allows without risking a cracked shell.
The pour itself is not the constraint. At 1420 °C into a 900 °C shell, the pour takes minutes, and holding a furnace open longer does not make the part earlier. The days sit in drying, in cooling and in the heat treatment hold.
Where a date is genuinely tight, the honest options are to release the tool earlier, to accept a partial shipment of machined parts, or to change the process. Promising a shorter vacuum investment casting lead time without one of those changes only moves the delay to the end.
Send the wall thickness, the inspection scope and the date you are working to, and we will return a working-day estimate with the machining block broken out before quoting.